Pump Station Rehabilitation Program East Basin, West Basin, and Edgewater Point Pump Stations

This $6.7 Million Project for Westchester County Department of Public Works was for the rehabilitation of the East Basin, West Basin, and Edgewater Point Pump Stations located in Mamaroneck, New York.

The project included the demolition of pumps, motors, HVAC, piping, valves, electric, controls and miscellaneous architectural features. ECCO furnished and installed bar screens, sluice gates, pumps, piping, valves, meters, bypass pumping vaults, plumbing and HVAC systems, odor control systems, electrical and controls, and various structural/architectural features. The pump stations were kept operational during construction using bypass pumping systems.

Contract No.

13-514

Owner

County of Westchester - Department of Public Works

Engineer of Record

GHD Consulting Engineers, LLC

Contract Value at Award

$6.7 Million

Award/Notice to Proceed

January 2016

Contract Completion

December 2017