ECCO III Enterprises, Inc.

Bridge Replacement of E 138th St over Major Deegan Expressway in the Borough of the Bronx​

This $47.3 Million project for the NYSDOT consists of the Replacement of the 138th Street Bridge over the Major Deegan Expressway in the Bronx, New York. This complex project requires expertise in managing a heavily congested worksite with ongoing vehicular and pedestrian traffic.

This Project will occur in a period of 10 stages, beginning with temporary utility installation and combined sewer relocation. Subsequently, Stages 2 through 5 will consist of bridge reconstruction. Finally, Stages 6 through 10 will consist of MDE pavement reconstruction. The Work includes drilled and driven piles, precast concrete/steel bridge units, SOE installation, multiple underground utility and structure relocations and concrete pavement reconstruction.

This project will require Third-Party coordination with Empire City Subway Communications, NYSDOT ITS and Con Edison Gas and Electric.

Contract No.

D264507

Owner

New York State Department of Transportation (NYSDOT)

Engineer of Record

Greenman-Pederson, Inc. (GPI)

Contract Value at Award

$47.3 Million

Award/Notice to Proceed

September 2021

Contract Completion

Ongoing